Use a parallel run to prove the new workflow

The old scheduling system and its replacement both show a filled shift. Only one includes the travel allowance that payroll expects. An operator looking at either schedule would say the shift is covered. The payroll export is where the difference appears.

A parallel run feeds the same real inputs through both workflows and checks the decisions and outputs side by side. Set one system to own every live action for the duration of the test.

One set of shifts, two independent results

  • Approved hours
  • Assignment rules
  • Current export
  • Proposed export

Approved hours, Assignment rules → Fixed cutoff → Current export, Proposed export

The proposed export is held for comparison while the current system owns submission.

Pick a period with the work people actually do

For a staffing team, that might mean a week covering a holiday, an overnight shift, and a corrected time sheet. Agree on the exact cutoff and export the same input set to both systems. Keep the old workflow responsible for submissions, emails, and any payments until you formally change ownership.

Run the new workflow with downstream actions disabled or sent to test destinations. Ask operators in advance which parts they should complete twice and how to flag a discrepancy without interrupting the live run.

Compare the outcome someone relies on

Check hours, allowance, employee ID, and pay period by assignment. The travel allowance may differ because the new workflow calculated the distance from the wrong site field. Record how to reproduce the result with approved test data and which team can fix it.

Some changes are intentional. If the new schedule shows an assignment under a different label, ask whether the downstream export uses the label or a stable code. Tolerances belong to the decision affected by the difference.

Keep the two output versions with the comparison. When someone changes a rule, check the records it should affect and a few it should leave alone. That helps catch a fix that corrects travel allowances by changing another part of the export.

End when the evidence is sufficient

Name who signs off on each output and which discrepancies hold the switch. Repeat an affected period after changing a calculation rule. Once owners accept the results, record when the new workflow takes over live actions and what checks the team will run on its first independent cycle.

More articles.

  1. Rehearse a legacy data migration with the people who use it

    Time the full migration, verify meaningful business records, and give operators a say in whether the new system is ready.

  2. Plan migration rollback around the first live write

    Set a stop point, decide what happens to work recorded after cutover, and rehearse how to restore a usable workflow.

  3. Make a system-of-record map before you integrate

    Decide which system owns each field, who can change it, and how corrections move between your CRM, order system, and accounting software.

All articles

Want a second opinion on your project?

Book a call and we’ll talk through your options.

JurajCEO, QikBuild

You leave the call with

  • What we would build first
  • A rough price range
  • Whether custom software makes sense for you
Book a 30-minute call

Or write to hello@qikbuild.com