Skip to content

Compare actuals with the forecast you made at the time

The Monday forecast said fifteen installations would finish this week. By Thursday, the team expected twelve. A report that keeps only Thursday’s plan shows perfect accuracy when twelve finish. It loses the information the team needed on Monday to schedule spare capacity.

Follow one reporting week from plan to review

  1. Save the baseline Monday’s forecast drives staffing
  2. Record revisions Keep each version and its reason
  3. Close the period Count completed jobs using an agreed event
  4. Review the difference Explain misses and revise the next plan

Capture the date and assumptions

Store the forecast for each team and period with the time it was recorded. Include the assumptions most likely to affect the plan, such as a second crew being available on Wednesday. Keep later revisions as new records and make the report label which snapshot it is showing.

In this illustrative week, three installations move because the site is inaccessible. All three came out of the Thursday plan. The report can show the three-job variance versus Monday and that the team completed the revised plan. Each answers a different question for the meeting.

Align the definition of actuals

A forecast of completed installations needs actuals from the close event, even if an invoice arrives later. Define how rebookings, partially finished jobs and late-entered completion dates affect the total. Let the team inspect the work items behind each week. They should be able to tie a missed forecast to one of the jobs they remember rescheduling.

Keep the explanation with the number

Use a short list of reasons, such as capacity, dependencies and demand. Leave room for a note on unusual weeks. Compare a few periods before changing the forecasting process. If the same dependency explains three misses in a row, the next plan can schedule those jobs only once the site is ready.

More articles.

  1. Write metric definitions that two departments can use

    Define the event, date and exceptions behind a KPI so people can trace it to records and explain differences between reports.

  2. Show how fresh a report is and handle late records

    Keep event time and processing time separate, show missing feeds and decide how corrections enter past reports.

  3. Plan team capacity from the work already in the queue

    Use task effort, availability and skills to see what a team can finish, with an example of a hidden staffing bottleneck.

All articles

Want a second opinion on your project?

Book a call and we’ll talk through your options.

JurajCEO, QikBuild

You leave the call with

  • What we would build first
  • A rough price range
  • Whether custom software makes sense for you
Book a 30-minute call

Or write to hello@qikbuild.com